Ramsey High School.

•Name & location of the project: Public works storage shed, Bergen County, New Jersey.

•Goods and services provided: The work involved installing a wooded truss system and a sloped roofing system.

•Start and completion dates: February 2005 - May 2005.

•Contract amount: $80,000.00.

New York City Department of Parks and Recreation.

•Name and location of the project: Von King Cultural Center, Brooklyn, New York.

•Goods and services provided: The work involved replacement of the metal standing seam roof.

•Start and completion dates: September 2007 - May 2008.

•Contract Amount: $190,000.00.

BOE Wappingers Central School District.

•Name and location of the project: Oak Grove Elementary School replacement of the existing (EPDM) roof system, structural.

•Goods and services provided: The scope of work involved removing and replacing 40,000s.f. of EPDM, new soffits and fascia system installed.

•Start and completion dates: June 2008 - September 2008

•Contract amount: $748,000.00.

Port Chester-Rye Union Free School District.

•Name and location of the project: Edison Elementary School, Port Chester, New York.

•Goods and services provided: The work involved removing and replacement of 13,000 s.f. of the asphalt shingle, structural rafters and gutters had to be extendeed to accommodate new soffit vents.

•Start and completion dates: June2008 - September 2008

•Contract amount: $280,000.00.

New York City School Construction Authority.

•Name and location of the project: Public School 332, Brooklyn, New York.

•Goods and services provided: The involved reconstruction of the existing auditorium with new interior walls, flooring, ceiling, seating and stage.

•Start and completion dates: March 2005 - December 2005.

•Contract amount: $320,000.00.

New York City Department of Parks and Recreation.

•Name and location of the project: Structural Reconstruction of interior sections of Gracie Mansion Historic House in Manhattan.

•Goods and services provided: The work involved roof replacement, structural steel installation, concrete and masonry reconstruction, carpentry and various other types of surface restorations.

•Start and completion dates: February 2004 - January 2005.

•Contract amount: $500,000.00.

New York City Department of Parks and Recreation.

•Name and location of the project: Citywide Structural Reconstruction of Pools, located throughout all five boroughs of New York City.

•Goods and services provided: The work involved pool tub and deck reconstruction, waterproofing, sealants,  structural steel grading, concrete and masonry reconstruction, carpentry and various other types of surface restoration.

•Start and completion dates: May 2005 - June 2006

•Contract amount: $550,000.00. 

New York City Department of Parks and Recreation.

•Name and location of the project: Structural reconstruction of interior sections of Gracie Mansion Historic House in Manhattan located at East 88 Street, New York, New York.

•Goods and services provided: The work involved roof replacement, structural steel installation, concrete and masonry reconstruction, carpentry and various other types of surfacerestorations.

•Start and completion dates: February 2004 - January 2005

•Contract amount: $500,000.00. 

Office of General Services.

•Name and location of the project: Removal and installation of new rubber roof located at 100 East 5th Street, Huntington Station, Long Island

•Goods and services provided: Removal and installation of built up roofing system.

•Start and completion dates: October 2007 - November 2007

•Contract amount: $136,000.00.

New York City Depamtment of Parks and Recreation.

•Name and location: Citywide structural reconstruction of pools.

•Goods and services: The work involved pool tub and deck reconstruction, waterproofing, sealants, structural steel grading, concrete & masonry reconstruction, carpentry and various other typesof surface restorations.

•Start and completion dates: May 2005 - June 2006

•Contract amount: 550,000.00.

Office of Parks, Recreation and Historic Preservation.

•Name and location of the project: Ice and Bathhouse Roof Replacement at Bear Mountain State Park, Town of Stony Point, Rockland County, New York.

•Goods and services provided: The work involved removing and installing new slate along with copper flashing.

•Start and completion dates: December 2007 - February 2009

•Contract amount: $210,450.00.

Peekskill City School District.

•Name and location of the project: Roof reconstruction at 1031 Elm Street.

•Goods and services provided: The work involved removal of existing slate and copper Yankee gutter; installation of new underlayment, snow guards, slate and gutter; chimney reconstruction, resetting of chimney coping stones and manufacturing custom chmney cap.

•Start and completion: - February 2009

•Contract amount: $300,000.00.

Scarsdale Union Free School District.

•Name and services provided: District wide roof repairs at 2 Brewster Road, Scarsdale, New York.

•Goods and services provided: The work included slate, built up, and EPDM repairs.

•Start and completion dates: January 2009 - February 2009

•Contract amount: $280,000.00.

Manhattan North Building Corporation.

•Name and services provided: Interior Alterationa at 118 West 112th Street, New York, New York.

•Goods and services provided:

•Start and completion dates: - February 2010

•Contract amount: $ 

New York City Depatrment of Sanitation

•Name and services provided:

•Goods and services provided:

•Start and completion dates:

•Conract amount: